Company : Usha Martin Ltd.
Environment Clearance | Forest Clearance

Javascript is required to view this map.
Facts
Sector
Coal Mining
NO. OF PROJECTS CLEARED
1
TOTAL LAND REQUIRED (ha.)
450.00
TOTAL WATER REQUIRED (m3/day)
302.55
TOTAL CAPACITY
0.20 MTPA
Sector
Iron and Steel
NO. OF PROJECTS CLEARED
2
TOTAL LAND REQUIRED (ha.)
157.98
TOTAL WATER REQUIRED (m3/day)
15550.00
TOTAL CAPACITY
2.20 MTPA
Sector
Iron Ore Mining
NO. OF PROJECTS CLEARED
1
TOTAL LAND REQUIRED (ha.)
155.08
TOTAL WATER REQUIRED (m3/day)
154.00
TOTAL CAPACITY
1.85 MTPA
Sector
Thermal Power Plant
NO. OF PROJECTS CLEARED
1
TOTAL LAND REQUIRED (ha.)
4.91
TOTAL WATER REQUIRED (m3/day)
624.00
TOTAL CAPACITY
20.00 MW